Thursday, April 17, 2003

April 17, 2003
390 hours completed

1. 10:00: Working on cleaning up the docs I scanned yesterday and inserting them into the Equine manual.
2. 4:30: Finished about half of the manual. I'll finish up on Monday, because tomorrow is Good Friday! Good Friday = Sleep + relaxation x happiness

Wednesday, April 16, 2003

April 16, 2003
382 hours completed

1. 10:00: Almost completed the ppt for the presentation next week. I have to email Nadine to see when we can finish scanning.
2. 3:40: I've been scanning since 11:00, and I'm finally finished now at 3:30. I still have a lot of cleanup to do on the docs, but they are there. I have a massive headache, and really need to get away from this screen.

Tuesday, April 15, 2003

April 15, 2003
373 hours completed

1. 12:15: I've been working on the disaster recovery files. I'm doing both pdf and a webpage, they can decide which one works better for them. After lunch I'll probably start my powerpoint presentation.
2. 4:15: I started my ppt and took some screenshots of my projects to add the the presentation. I also observed the setup and use of a KVM switch (16 port dual monitor)

Monday, April 14, 2003

April 14, 2003
365 hours

1. 9:00: Working on my presentation, due next Wednesday
2. 4:20: Spent some time this afternoon working on disaster recovery file (pdf). Chris S. stopped by to talk about it with me, and he emailed me some additional files.